Construction Lien Act
R.S.O. 1990, CHAPTER C.30
Consolidation Period: From May 1, 2007 to the e-Laws currency date.
Last amendment: 2006, c. 21, Sched. C, s. 102.
CONTENTS
Interpretation | |
Contracts, substantial performance and completion | |
PART I | |
Act binds Crown | |
No waiver of rights | |
Contracts to conform | |
Minor irregularities | |
PART II | |
Owner’s trust | |
Contractor’s and subcontractor’s trust | |
Vendor’s trust | |
Payment discharging trust | |
Where trust funds may be reduced | |
Set-off by trustee | |
Liability for breach of trust | |
PART III | |
Creation of lien | |
When lien arises | |
Interest of Crown | |
Limitation on value of lien | |
Joint or common interests | |
Where owner’s interest leasehold | |
General lien, more than one premises | |
Lien a charge | |
PART IV | |
Holdbacks | |
Personal liability of owner | |
Payments that may be made | |
Payment where subcontract certified complete | |
Payment of basic holdback | |
Payment of holdback for finishing work | |
Direct payment to person having lien | |
Discharge of lien | |
How holdback not to be applied | |
PART V | |
Expiry of liens | |
Rules governing certification or declaration of substantial performance | |
Certificate re subcontract | |
How lien preserved | |
Liability for exaggerated claim, etc. | |
What liens may be perfected | |
Expiry of perfected lien | |
Saving other rights | |
PART VI | |
Right to information; | |
Cross-examination on claim for lien | |
PART VII | |
Discharge of lien and withdrawal of written notice of lien | |
Discharge of general lien | |
Postponement of lien claim | |
Vacating lien by payment into court | |
Declaration by court that preserved lien has expired | |
Order dismissing action, etc. | |
General power to discharge lien | |
Discharge irrevocable | |
Registration of orders | |
PART VIII | |
Lien claims and trust claims | |
Court to dispose completely of action | |
Where exclusive jurisdiction not acquired | |
Statement of claim and defence | |
Time for delivery of pleadings | |
Accommodating multiple claims | |
Rules re third party claims | |
Parties | |
Reference to master, etc. | |
Carriage of action | |
Application to fix date for trial or settlement meeting | |
Conduct of settlement meeting | |
Judgment or report | |
Personal judgment | |
Right to share in proceeds | |
Orders for completion of sale | |
Application to court for directions | |
Procedure generally | |
PART IX | |
Application for appointment of trustee | |
Labour and material payment bonds | |
PART X | |
Stated case | |
Appeal to Divisional Court | |
PART XI | |
Enforcement of lien despite default | |
Assignment of lien rights | |
Continuation of general lien | |
Effect of taking security | |
Lien claimant deemed purchaser | |
Priority of liens over executions, etc. | |
Priority over mortgages, etc. | |
Persons who comprise class | |
Priority between and within class | |
Worker’s priority | |
Subordination of general lien claims | |
Application of insurance proceeds | |
Distribution of proceeds of sale | |
Priorities on insolvency | |
PART XII | |
Costs | |
How documents may be given | |
Regulations | |
Interpretation
Definitions
“action” means an action under Part VIII; (“action”)
“construction trade newspaper” means a newspaper having circulation generally throughout Ontario, that is published no less frequently than on all days except Saturdays and holidays, and in which calls for tender on construction contracts are customarily published, and that is primarily devoted to the publication of matters of concern to the construction industry; (“journal de l’industrie de la construction”)
“contract” means the contract between the owner and the contractor, and includes any amendment to that contract; (“contrat”)
“contractor” means a person contracting with or employed directly by the owner or an agent of the owner to supply services or materials to an improvement; (“entrepreneur”)
“court” means the Superior Court of Justice; (“tribunal”)
“Crown” includes a Crown agency to which the Crown Agency Act applies; (“Couronne”)
“holdback” means the 10 per cent of the value of the services or materials supplied under a contract or subcontract required to be withheld from payment by Part IV; (“retenue”)
“home” means,
(a) a self-contained one-family dwelling, detached or attached to one or more others by a common wall,
(b) a building composed of two self-contained, one-family dwellings under one ownership, or
(c) a condominium one-family dwelling unit, including the common interests appurtenant thereto,
and includes any structure or works used in conjunction therewith; (“logement”)
“home buyer” means a person who buys the interest of an owner in a premises that is a home, whether built or not at the time the agreement of purchase and sale in respect thereof is entered into, provided,
(a) not more than 30 per cent of the purchase price, excluding money held in trust under section 53 of the Condominium Act, is paid prior to the conveyance, and
(b) the home is not conveyed until it is ready for occupancy, evidenced in the case of a new home by the issuance of a municipal permit authorizing occupancy or the issuance under the Ontario New Home Warranties Plan Act of a certificate of completion and possession; (“acquéreur d’un logement”)
“improvement” means,
(a) any alteration, addition or repair to, or
(b) any construction, erection or installation on,
any land, and includes the demolition or removal of any building, structure or works or part thereof, and “improved” has a corresponding meaning; (“améliorations”, “amélioré”)
“interest in the premises” means an estate or interest of any nature, and includes a statutory right given or reserved to the Crown to enter any lands or premises belonging to any person or public authority for the purpose of doing any work, construction, repair or maintenance in, upon, through, over or under any lands or premises; (“intérêt sur le local”)
“land” includes any building, structure or works affixed to the land, or an appurtenance to any of them, but does not include the improvement; (“bien-fonds”)
“lien claimant” means a person having a preserved or perfected lien; (“créancier privilégié”)
“materials” means every kind of movable property,
(a) that becomes, or is intended to become, part of the improvement, or that is used directly in the making of the improvement, or that is used to facilitate directly the making of the improvement,
(b) that is equipment rented without an operator for use in the making of the improvement; (“matériaux”)
“mortgage” includes a charge and “mortgagee” includes a chargee; (“hypothèque”, “créancier hypothécaire”)
“municipality” means a municipality or local board, both as defined in the Municipal Affairs Act; (“municipalité”)
“owner” means any person, including the Crown, having an interest in a premises at whose request and,
(a) upon whose credit, or
(b) on whose behalf, or
(c) with whose privity or consent, or
(d) for whose direct benefit,
an improvement is made to the premises but does not include a home buyer; (“propriétaire”)
“payer” means the owner, contractor or subcontractor who is liable to pay for the materials or services supplied to an improvement under a contract or subcontract; (“responsable du paiement”)
“payment certifier” means an architect, engineer or any other person upon whose certificate payments are made under a contract or subcontract; (“personne qui autorise le paiement”)
“person having a lien” includes both a lien claimant and a person with an unpreserved lien; (“titulaire d’un privilège”)
“premises” includes,
(a) the improvement,
(b) all materials supplied to the improvement, and
(c) the land occupied by the improvement, or enjoyed therewith, or the land upon or in respect of which the improvement was done or made; (“local”)
“price” means the contract or subcontract price,
(a) agreed upon between the parties, or
(b) where no specific price has been agreed upon between them, the actual value of the services or materials that have been supplied to the improvement under the contract or subcontract; (“prix”)
“services or materials” includes both services and materials; (“services ou matériaux”)
“subcontract” means any agreement between the contractor and a subcontractor, or between two or more subcontractors, relating to the supply of services or materials to the improvement and includes any amendment to that agreement; (“contrat de sous-traitance”)
“subcontractor” means a person not contracting with or employed directly by the owner or an agent of the owner but who supplies services or materials to the improvement under an agreement with the contractor or under the contractor with another subcontractor; (“sous-traitant”)
“suffers damages as a result” means suffers damages that could be reasonably foreseen to result; (“subir des dommages en conséquence”)
“supply of services” means any work done or service performed upon or in respect of an improvement, and includes,
(a) the rental of equipment with an operator, and
(b) where the making of the planned improvement is not commenced, the supply of a design, plan, drawing or specification that in itself enhances the value of the owner’s interest in the land,
and a corresponding expression has a corresponding meaning; (“prestation de services”)
“wages” means the money earned by a worker for work done by time or as piece work, and includes all monetary supplementary benefits, whether provided for by statute, contract or collective bargaining agreement; (“salaire”)
“worker” means a person employed for wages in any kind of labour; (“ouvrier”)
“workers’ trust fund” means any trust fund maintained in whole or in part on behalf of any worker on an improvement and into which any monetary supplementary benefit is payable as wages for work done by the worker in respect of the improvement; (“fonds en fiducie des ouvriers”)
“written notice of a lien” includes a claim for lien and any written notice given by a person having a lien that,
(a) identifies the payer and identifies the premises, and
(b) states the amount that the person has not been paid and is owed to the person by the payer. (“avis écrit d’un privilège”) R.S.O. 1990, c. C.30, s. 1 (1); 2002, c. 17, Sched. F, Table; 2006, c. 19, Sched. C, s. 1 (1).
When materials supplied
(2) For the purposes of this Act, materials are supplied to an improvement when they are,
(a) placed on the land on which the improvement is being made;
(b) placed upon land designated by the owner or an agent of the owner that is in the immediate vicinity of the premises, but placing materials on the land so designated does not, of itself, make that land subject to a lien; or
(c) in any event, incorporated into or used in making or facilitating directly the making of the improvement. R.S.O. 1990, c. C.30, s. 1 (2).
Idem
(3) A contractor or subcontractor to whom materials are supplied and who designates land under clause (2) (b) is deemed to be the owner’s agent for that purpose, unless the person supplying the materials has actual notice to the contrary. R.S.O. 1990, c. C.30, s. 1 (3).
Contracts, substantial performance and completion
When contract substantially performed
2. (1) For the purposes of this Act, a contract is substantially performed,
(a) when the improvement to be made under that contract or a substantial part thereof is ready for use or is being used for the purposes intended; and
(b) when the improvement to be made under that contract is capable of completion or, where there is a known defect, correction, at a cost of not more than,
(i) 3 per cent of the first $500,000 of the contract price,
(ii) 2 per cent of the next $500,000 of the contract price, and
(iii) 1 per cent of the balance of the contract price. R.S.O. 1990, c. C.30, s. 2 (1).
Idem
(2) For the purposes of this Act, where the improvement or a substantial part thereof is ready for use or is being used for the purposes intended and the remainder of the improvement cannot be completed expeditiously for reasons beyond the control of the contractor or, where the owner and the contractor agree not to complete the improvement expeditiously, the price of the services or materials remaining to be supplied and required to complete the improvement shall be deducted from the contract price in determining substantial performance. R.S.O. 1990, c. C.30, s. 2 (2).
When contract deemed completed
(3) For the purposes of this Act, a contract shall be deemed to be completed and services or materials shall be deemed to be last supplied to the improvement when the price of completion, correction of a known defect or last supply is not more than the lesser of,
(a) 1 per cent of the contract price; and
(b) $1,000. R.S.O. 1990, c. C.30, s. 2 (3).
Act binds Crown
3. (1) Subject to section 16 (where lien does not attach to the premises), this Act binds the Crown. R.S.O. 1990, c. C.30, s. 3 (1).
Exception re certain payments
(2) This Act does not apply in respect of labour, material or services supplied as a result of a contract, as defined in the Ministry of Transportation and Communications Creditors Payment Act, being chapter 290 of the Revised Statutes of Ontario, 1980, made before the 1st day of April, 1990. R.S.O. 1990, c. C.30, s. 3 (2).
Exception re notice of claim
(3) Section 7 of the Proceedings Against the Crown Act does not apply in respect of an action against the Crown under this Act. R.S.O. 1990, c. C.30, s. 3 (3).
(4) Repealed: 1997, c. 23, s. 4 (1).
No waiver of rights
4. An agreement by any person who supplies services or materials to an improvement that this Act does not apply to the person or that the remedies provided by it are not available for the benefit of the person is void. R.S.O. 1990, c. C.30, s. 4.
Contracts to conform
5. (1) Every contract or subcontract related to an improvement is deemed to be amended in so far as is necessary to be in conformity with this Act. R.S.O. 1990, c. C.30, s. 5 (1).
Retention of holdbacks authorized
(2) Without restricting the generality of subsection (1), where the purchaser is an owner, an agreement of purchase and sale that provides for the making or completion of an improvement shall be deemed to provide for the retention of holdbacks by the purchaser, and tender by the purchaser on closing is not defective by reason only that the purchaser does not tender the amount of the holdbacks. R.S.O. 1990, c. C.30, s. 5 (2).
Minor irregularities
6. No certificate, declaration or claim for lien is invalidated by reason only of a failure to comply strictly with subsection 32 (2) or (5), subsection 33 (1) or subsection 34 (5), unless in the opinion of the court a person has been prejudiced thereby, and then only to the extent of the prejudice suffered. R.S.O. 1990, c. C.30, s. 6.
Owner’s trust
Amounts received for financing a trust
7. (1) All amounts received by an owner, other than the Crown or a municipality, that are to be used in the financing of the improvement, including any amount that is to be used in the payment of the purchase price of the land and the payment of prior encumbrances, constitute, subject to the payment of the purchase price of the land and prior encumbrances, a trust fund for the benefit of the contractor. R.S.O. 1990, c. C.30, s. 7 (1).
Amounts certified as payable
(2) Where amounts become payable under a contract to a contractor by the owner on a certificate of a payment certifier, an amount that is equal to an amount so certified that is in the owner’s hands or received by the owner at any time thereafter constitutes a trust fund for the benefit of the contractor. R.S.O. 1990, c. C.30, s. 7 (2).
Where substantial performance certified
(3) Where the substantial performance of a contract has been certified, or has been declared by the court, an amount that is equal to the unpaid price of the substantially performed portion of the contract that is in the owner’s hands or is received by the owner at any time thereafter constitutes a trust fund for the benefit of the contractor. R.S.O. 1990, c. C.30, s. 7 (3).
Obligations as trustee
(4) The owner is the trustee of the trust fund created by subsection (1), (2) or (3), and the owner shall not appropriate or convert any part of a fund to the owner’s own use or to any use inconsistent with the trust until the contractor is paid all amounts related to the improvement owed to the contractor by the owner. R.S.O. 1990, c. C.30, s. 7 (4).
Contractor’s and subcontractor’s trust
Amounts received a trust
(a) owing to a contractor or subcontractor, whether or not due or payable; or
(b) received by a contractor or subcontractor,
on account of the contract or subcontract price of an improvement constitute a trust fund for the benefit of the subcontractors and other persons who have supplied services or materials to the improvement who are owed amounts by the contractor or subcontractor. R.S.O. 1990, c. C.30, s. 8 (1).
Obligations as trustee
(2) The contractor or subcontractor is the trustee of the trust fund created by subsection (1) and the contractor or subcontractor shall not appropriate or convert any part of the fund to the contractor’s or subcontractor’s own use or to any use inconsistent with the trust until all subcontractors and other persons who supply services or materials to the improvement are paid all amounts related to the improvement owed to them by the contractor or subcontractor. R.S.O. 1990, c. C.30, s. 8 (2).
Vendor’s trust
Amounts received a trust
9. (1) Where the owner’s interest in a premises is sold by the owner, an amount equal to,
(a) the value of the consideration received by the owner as a result of the sale,
less,
(b) the reasonable expenses arising from the sale and the amount, if any, paid by the vendor to discharge any existing mortgage indebtedness on the premises,
constitutes a trust fund for the benefit of the contractor. R.S.O. 1990, c. C.30, s. 9 (1).
Obligations as trustee
(2) The former owner is the trustee of the trust created by subsection (1), and shall not appropriate or convert any part of the trust property to the former owner’s own use or to any use inconsistent with the trust until the contractor is paid all amounts owed to the contractor that relate to the improvement. R.S.O. 1990, c. C.30, s. 9 (2).
Payment discharging trust
10. Subject to Part IV (holdbacks), every payment by a trustee to a person the trustee is liable to pay for services or materials supplied to the improvement discharges the trust of the trustee making the payment and the trustee’s obligations and liability as trustee to all beneficiaries of the trust to the extent of the payment made by the trustee. R.S.O. 1990, c. C.30, s. 10.
Where trust funds may be reduced
11. (1) Subject to Part IV, a trustee who pays in whole or in part for the supply of services or materials to an improvement out of money that is not subject to a trust under this Part may retain from trust funds an amount equal to that paid by the trustee without being in breach of the trust. R.S.O. 1990, c. C.30, s. 11 (1).
Application of trust funds to discharge loan
(2) Subject to Part IV, where a trustee pays in whole or in part for the supply of services or materials to an improvement out of money that is loaned to the trustee, trust funds may be applied to discharge the loan to the extent that the lender’s money was so used by the trustee, and the application of trust money does not constitute a breach of the trust. R.S.O. 1990, c. C.30, s. 11 (2).
Set-off by trustee
12. Subject to Part IV, a trustee may, without being in breach of trust, retain from trust funds an amount that, as between the trustee and the person the trustee is liable to pay under a contract or subcontract related to the improvement, is equal to the balance in the trustee’s favour of all outstanding debts, claims or damages, whether or not related to the improvement. R.S.O. 1990, c. C.30, s. 12.
Liability for breach of trust
By corporation
13. (1) In addition to the persons who are otherwise liable in an action for breach of trust under this Part,
(a) every director or officer of a corporation; and
(b) any person, including an employee or agent of the corporation, who has effective control of a corporation or its relevant activities,
who assents to, or acquiesces in, conduct that he or she knows or reasonably ought to know amounts to breach of trust by the corporation is liable for the breach of trust. R.S.O. 1990, c. C.30, s. 13 (1).
Effective control of corporation
(2) The question of whether a person has effective control of a corporation or its relevant activities is one of fact and in determining this the court may disregard the form of any transaction and the separate corporate existence of any participant. R.S.O. 1990, c. C.30, s. 13 (2).
Joint and several liability
(3) Where more than one person is found liable or has admitted liability for a particular breach of trust under this Part, those persons are jointly and severally liable. R.S.O. 1990, c. C.30, s. 13 (3).
Contribution
(4) A person who is found liable, or who has admitted liability, for a particular breach of a trust under this Part is entitled to recover contribution from any other person also liable for the breach in such amount as will result in equal contribution by all parties liable for the breach unless the court considers such apportionment would not be fair and, in that case, the court may direct such contribution or indemnity as the court considers appropriate in the circumstances. R.S.O. 1990, c. C.30, s. 13 (4).
Creation of lien
14. (1) A person who supplies services or materials to an improvement for an owner, contractor or subcontractor, has a lien upon the interest of the owner in the premises improved for the price of those services or materials. R.S.O. 1990, c. C.30, s. 14 (1).
Note: Subsection (1) applies to services and materials supplied by architects, holders of certificates of practice under the Architects Act and their employees under contracts made on or after November 28, 1997, and under subcontracts made under such contracts. See: 1997, c. 23, s. 4 (2).
No lien for interest
(2) No person is entitled to a lien for any interest on the amount owed to the person in respect of the services or materials that have been supplied by the person, but nothing in this subsection affects any right that the person may otherwise have to recover that interest. R.S.O. 1990, c. C.30, s. 14 (2).
When lien arises
15. A person’s lien arises and takes effect when the person first supplies services or materials to the improvement. R.S.O. 1990, c. C.30, s. 15.
Interest of Crown
16. (1) A lien does not attach to the interest of the Crown in a premises. R.S.O. 1990, c. C.30, s. 16 (1).
Interest of person other than Crown
(2) Where an improvement is made to a premises in which the Crown has an interest, but the Crown is not an owner within the meaning of this Act, the lien may attach to the interest of any other person in that premises. R.S.O. 1990, c. C.30, s. 16 (2).
Where lien does not attach to premises
(3) Where the Crown is the owner of a premises within the meaning of this Act, or where the premises is,
(a) a public street or highway owned by a municipality; or
(b) a railway right-of-way,
the lien does not attach to the premises but constitutes a charge as provided in section 21, and the provisions of this Act shall have effect without requiring the registration of a claim for lien against the premises. R.S.O. 1990, c. C.30, s. 16 (3).
Limitation on value of lien
17. (1) The lien of a person is limited to the amount owing to the person in relation to the improvement and, subject to Part IV (holdbacks), it is further limited to the least amount owed in relation to the improvement by a payer to the contractor or to any subcontractor whose contract or subcontract was in whole or in part performed by the supply of services or materials giving rise to the lien. R.S.O. 1990, c. C.30, s. 17 (1).
Idem
(2) Subject to Part IV, the total value of the liens of all members of a class, as defined in section 79, is limited to the least amount owed in relation to the improvement by a payer to the contractor or to any subcontractor whose contract or subcontract was in whole or in part performed by the supply of services or materials made by the members of the class. R.S.O. 1990, c. C.30, s. 17 (2).
Set-off
(3) Subject to Part IV, in determining the amount of a lien under subsection (1) or (2), there may be taken into account the amount that is, as between a payer and the person the payer is liable to pay, equal to the balance in the payer’s favour of all outstanding debts, claims or damages, whether or not related to the improvement. R.S.O. 1990, c. C.30, s. 17 (3).
Public highway, liability of municipality re
(4) Despite subsection (1), where land is dedicated to a municipality as a public street or highway and an improvement is made to the land at the written request of, or under an agreement with, the municipality, but not at its expense, the municipality shall nevertheless, on default of payment by the proper payer, be liable to the value of the holdbacks under Part IV that would have been required were the improvement made at the expense of the municipality, and the procedure for making a claim under this subsection shall be the same as for enforcing a claim for lien against a municipality in respect of a public street or highway. R.S.O. 1990, c. C.30, s. 17 (4).
Joint or common interests
18. Where the interest of the owner in the premises is held jointly or in common with another person who knew or ought reasonably to have known of the making of the improvement, the joint or common interest in the premises of that person is also subject to the lien unless the contractor receives actual notice, before the supply of services or materials to the improvement is commenced, that the person having the joint or common interest assumes no responsibility for the improvement to be made. R.S.O. 1990, c. C.30, s. 18.
Where owner’s interest leasehold
19. (1) Where the interest of the owner to which the lien attaches is leasehold, the interest of the landlord shall also be subject to the lien to the same extent as the interest of the owner if the contractor gives the landlord written notice of the improvement to be made, unless the landlord, within fifteen days of receiving the notice from the contractor, gives the contractor written notice that the landlord assumes no responsibility for the improvement to be made. R.S.O. 1990, c. C.30, s. 19 (1).
Forfeiture or termination of lease, effect of
(2) No forfeiture of a lease to, or termination of a lease by, a landlord, except for non-payment of rent, deprives any person having a lien against the leasehold of the benefit of the person’s lien. R.S.O. 1990, c. C.30, s. 19 (2).
Notice to lien claimants
(3) Where a landlord intends to enforce forfeiture or terminate a lease of the premises because of non-payment of rent, and there is a claim for lien registered against the premises in the proper land registry office, the landlord shall give notice in writing of the intention to enforce forfeiture or terminate the lease and of the amount of the unpaid rent to each person who has registered a claim for lien against the premises. R.S.O. 1990, c. C.30, s. 19 (3).
Payment of unpaid rent
(4) A person receiving notice under subsection (3) may, within ten days thereafter, pay to the landlord the amount of the unpaid rent, and the amount so paid may be added by that person to the person’s claim for lien. R.S.O. 1990, c. C.30, s. 19 (4).
General lien, more than one premises
20. (1) Where an owner enters into a single contract for improvements on more than one premises of the owner, any person supplying services or materials under that contract, or under a subcontract under that contract, may choose to have the person’s lien follow the form of the contract and be a general lien against each of those premises for the price of all services and materials the person supplied to all the premises. R.S.O. 1990, c. C.30, s. 20 (1).
Where subs. (1) does not apply
(2) Subsection (1) does not apply and no general lien arises under or in respect of a contract that provides in writing that liens shall arise and expire on a lot-by-lot basis. R.S.O. 1990, c. C.30, s. 20 (2).
Lien a charge
21. The lien of a person is a charge upon the holdbacks required to be retained by Part IV, and subject to subsection 17 (3), any additional amount owed in relation to the improvement by a payer to the contractor or to any subcontractor whose contract or subcontract was in whole or in part performed by the supply of services or materials giving rise to the lien. R.S.O. 1990, c. C.30, s. 21.
Holdbacks
Basic holdback
22. (1) Each payer upon a contract or subcontract under which a lien may arise shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied under the contract or subcontract until all liens that may be claimed against the holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44 (payment into court). R.S.O. 1990, c. C.30, s. 22 (1).
Separate holdback for finishing work
(2) Where the contract has been certified or declared to be substantially performed but services or materials remain to be supplied to complete the contract, the payer upon the contract, or a subcontract, under which a lien may arise shall retain, from the date certified or declared to be the date of substantial performance of the contract, a separate holdback equal to 10 per cent of the price of the remaining services or materials as they are actually supplied under the contract or subcontract, until all liens that may be claimed against the holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44. R.S.O. 1990, c. C.30, s. 22 (2).
When obligation to retain applies
(3) The obligation to retain the holdbacks under subsections (1) and (2) applies irrespective of whether the contract or subcontract provides for partial payments or payment on completion. R.S.O. 1990, c. C.30, s. 22 (3).
Personal liability of owner
23. (1) Subject to subsections (2), (3) and (4), an owner is personally liable for holdbacks that the owner is required to retain under this Part to those lien claimants who have valid liens against the owner’s interest in the premises. R.S.O. 1990, c. C.30, s. 23 (1).
Limitation
(2) Where the defaulting payer is the contractor, the owner’s personal liability to a lien claimant or to a class of lien claimants as defined by section 79 does not exceed the holdbacks the owner is required to retain. R.S.O. 1990, c. C.30, s. 23 (2).
Idem
(3) Where the defaulting payer is a subcontractor, the owner’s personal liability to a lien claimant or to a class of lien claimants as defined by section 79 does not exceed the lesser of,
(a) the holdbacks the owner is required to retain; and
(b) the holdbacks required to be retained by the contractor or a subcontractor from the lien claimant’s defaulting payer. R.S.O. 1990, c. C.30, s. 23 (3).
How determined
(4) The personal liability of an owner under this section may only be determined by an action under this Act. R.S.O. 1990, c. C.30, s. 23 (4).
Transition
(5) This section does not affect the rights acquired by any person from a judgment or order of any court before the 28th day of June, 1990. R.S.O. 1990, c. C.30, s. 23 (5).
Payments that may be made
24. (1) A payer may, without jeopardy, make payments on a contract or subcontract up to 90 per cent of the price of the services or materials that have been supplied under that contract or subcontract unless, prior to making payment, the payer has received written notice of a lien. R.S.O. 1990, c. C.30, s. 24 (1).
Idem
(2) Where a payer has received written notice of a lien and has retained, in addition to the holdbacks required by this Part, an amount sufficient to satisfy the lien, the payer may, without jeopardy, make payment on a contract or subcontract up to 90 per cent of the price of the services and materials that have been supplied under that contract or subcontract, less the amount retained. R.S.O. 1990, c. C.30, s. 24 (2).
Payment where subcontract certified complete
25. Where a subcontract has been certified complete under section 33, each payer upon the contract and any subcontract may, without jeopardy, make payment reducing the holdbacks required by this Part to the extent of the amount of holdback the payer has retained in respect of the completed subcontract, where all liens in respect of the completed subcontract have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44 (payment into court). R.S.O. 1990, c. C.30, s. 25.
Payment of basic holdback
26. Each payer upon the contract or a subcontract may, without jeopardy, make payment of the holdback the payer is required to retain by subsection 22 (1) (basic holdback), so as to discharge all claims in respect of that holdback, where all liens that may be claimed against that holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44. R.S.O. 1990, c. C.30, s. 26.
Payment of holdback for finishing work
27. Each payer upon the contract or a subcontract may, without jeopardy, make payment of the holdback the payer is required to retain by subsection 22 (2) (holdback for finishing work), so as to discharge all claims in respect of that holdback, where all liens that may be claimed against that holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44. R.S.O. 1990, c. C.30, s. 27.
Direct payment to person having lien
28. Where an owner, contractor or subcontractor makes a payment without obligation to do so to any person having a lien for or on account of any amount owing to that person for services or materials supplied to the improvement and gives written notice of the payment or the intention to pay to the proper payer of that person, the payment shall be deemed to be a payment by the owner, contractor or subcontractor to the proper payer of that person, but no such payment reduces the amount of the holdback required to be retained under this Part or reduces the amount that must be retained in response to a written notice of lien given by a person other than the person to whom payment is made. R.S.O. 1990, c. C.30, s. 28.
Discharge of lien
29. Payments made in accordance with this Part operate as a discharge of the lien to the extent of the amount paid. R.S.O. 1990, c. C.30, s. 29.
How holdback not to be applied
30. Where the contractor or a subcontractor defaults in the performance of a contract or subcontract, a holdback shall not be applied by any payer toward obtaining services or materials in substitution for those that were to have been supplied by the person in default, nor in payment or satisfaction of any claim against the person in default, until all liens that may be claimed against that holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44 (payment into court). R.S.O. 1990, c. C.30, s. 30.
PART V
EXPIRY, PRESERVATION AND PERFECTION OF LIENS
Expiry of liens
31. (1) Unless preserved under section 34, the liens arising from the supply of services or materials to an improvement expire as provided in this section. R.S.O. 1990, c. C.30, s. 31 (1).
Contractor’s liens
(2) Subject to subsection (4), the lien of a contractor,
(a) for services or materials supplied to an improvement on or before the date certified or declared to be the date of the substantial performance of the contract, expires at the conclusion of the forty-five-day period next following the occurrence of the earlier of,
(i) the date on which a copy of the certificate or declaration of the substantial performance of the contract is published as provided in section 32, and
(ii) the date the contract is completed or abandoned; and
(b) for services or materials supplied to the improvement where there is no certification or declaration of the substantial performance of the contract, or for services or materials supplied to the improvement after the date certified or declared to be the date of substantial performance, expires at the conclusion of the forty-five-day period next following the occurrence of the earlier of,
(i) the date the contract is completed, and
(ii) the date the contract is abandoned. R.S.O. 1990, c. C.30, s. 31 (2).
Liens of other persons
(3) Subject to subsection (4), the lien of any other person,
(a) for services or materials supplied to an improvement on or before the date certified or declared to be the date of the substantial performance of the contract, expires at the conclusion of the forty-five-day period next following the occurrence of the earliest of,
(i) the date on which a copy of the certificate or declaration of the substantial performance of the contract is published, as provided in section 32, and
(ii) the date on which the person last supplies services or materials to the improvement, and
(iii) the date a subcontract is certified to be completed under section 33, where the services or materials were supplied under or in respect of that subcontract; and
(b) for services or materials supplied to the improvement where there is no certification or declaration of the substantial performance of the contract, or for services or materials supplied to the improvement after the date certified or declared to be the date of the substantial performance of the contract, expires at the conclusion of the forty-five-day period next following the occurrence of the earlier of,
(i) the date on which the person last supplied services or materials to the improvement, and
(ii) the date a subcontract is certified to be completed under section 33, where the services or materials were supplied under or in respect of that subcontract. R.S.O. 1990, c. C.30, s. 31 (3).
Separate liens when ongoing supply
(4) Where a person has supplied services or materials to an improvement on or before the date certified or declared to be the date of the substantial performance of the contract and has also supplied, or is to supply, services or materials after that date, the person’s lien in respect of the services or materials supplied on or before the date of substantial performance expires without affecting any lien that the person may have for the supply of services or materials after that date. R.S.O. 1990, c. C.30, s. 31 (4).
Declaration of last supply
(5) Where a person who has supplied services or materials under a contract or subcontract makes a declaration in the prescribed form declaring,
(a) the date on which the person last supplied services or materials under that contract or subcontract; and
(b) that the person will not supply any further services or materials under that contract or subcontract,
then the facts so stated shall be deemed to be true against the person making the declaration. R.S.O. 1990, c. C.30, s. 31 (5).
Rules governing certification or declaration of substantial performance
32. (1) The following rules govern the certification and declaration of the substantial performance of a contract:
1. On the application of the contractor, the payment certifier shall determine whether the contract has been substantially performed in accordance with section 2, and, if the payment certifier so determines, shall certify the substantial performance of the contract by signing a certificate in the prescribed form. If there is no payment certifier, the owner and contractor shall make the determination jointly and shall both sign the certificate.
2. The payment certifier or the owner and the contractor jointly, as the case may be, shall set out in the certificate the date on which the contract was substantially performed.
3. The date set out in the certificate as the date on which the contract was substantially performed is deemed for the purpose of this Act to be the date on which that event occurred.
4. Where the payment certifier certifies the substantial performance of a contract the payment certifier shall within seven days of the day the certificate is signed give a copy of the certificate to the owner and to the contractor.
5. The contractor shall publish a copy of the certificate once in a construction trade newspaper.
6. Where the contractor does not publish a copy of the certificate within seven days of receiving a copy of the certificate signed by the payment certifier or, where there is no payment certifier, signed by the owner, any person may publish a copy of the certificate.
7. Where there is a failure or refusal to certify substantial performance of the contract within a reasonable time, any person may apply to the court, and the court, upon being satisfied that the contract is substantially performed, and upon such terms as to costs or otherwise as it considers fit, may declare that the contract has been substantially performed, and the declaration has the same force and effect as a certificate of substantial performance of the contract.
8. Unless the court otherwise orders, the day the declaration is made shall be deemed to be the date the contract was substantially performed.
9. The person who applied to the court shall publish a copy of the declaration of substantial performance once in a construction trade newspaper.
10. For the purposes of this Part, a certificate or declaration of the substantial performance of a contract has no effect until a copy of the certificate or declaration is published. R.S.O. 1990, c. C.30, s. 32 (1).
Contents of certificate
(2) Every certificate or declaration made or given under this section shall include,
(a) the name and address for service of the owner and of the contractor;
(b) the name and address of the payment certifier, where there is one;
(c) a short description of the improvement;
(d) the date on which the contract was substantially performed;
(e) where the lien attaches to the premises, a concise description containing a reference to lot and plan or instrument registration number sufficient to identify the premises; and
(f) the street address, if any, of the premises. R.S.O. 1990, c. C.30, s. 32 (2).
Liability for refusal to certify
(3) Any person who is required by this section to make a determination of the substantial performance of a contract, and who after receiving an application fails or refuses within a reasonable time to certify the substantial performance of the contract, even though there is no reasonable doubt that the contract has, in fact, been substantially performed, is liable to anyone who suffers damages as a result. R.S.O. 1990, c. C.30, s. 32 (3).
Liability for failure to furnish copy of certificate
(4) A payment certifier who fails to comply with paragraph 4 of subsection (1) is liable to anyone who suffers damages as a result. R.S.O. 1990, c. C.30, s. 32 (4).
Manner of publication
(5) A construction trade newspaper shall publish upon commercially reasonable terms copies of certificates or declarations of substantial performance in the prescribed form and manner. R.S.O. 1990, c. C.30, s. 32 (5).
Certificate re subcontract
33. (1) Upon the request of the contractor, the payment certifier on the contract may determine whether a subcontract has been completed, and, if the payment certifier so determines, shall certify the completion of the subcontract in the prescribed form; alternatively, the owner and the contractor may jointly make the declaration and certify completion in the prescribed form. R.S.O. 1990, c. C.30, s. 33 (1).
Date subcontract deemed completed
(2) Where a subcontract is certified to be completed, the subcontract shall be deemed to have been completed on the date of certification. R.S.O. 1990, c. C.30, s. 33 (2).
Services or materials supplied after subcontract certified completed
(3) If services or materials are supplied to the improvement under or in respect of a subcontract after the date the subcontract is certified to be completed, those services or materials shall be deemed to have been last supplied on the date of certification. R.S.O. 1990, c. C.30, s. 33 (3).
Copy of certificate
(4) Within seven days of the date the subcontract is certified to be completed, the payment certifier or the owner and the contractor, as the case may be, shall give a copy of the certificate,
(a) to the subcontractor whose subcontract has been certified as complete; and
(b) to the owner and the contractor, where certification is by the payment certifier. R.S.O. 1990, c. C.30, s. 33 (4).
How lien preserved
34. (1) A lien may be preserved during the supplying of services or materials or at any time before it expires,
(a) where the lien attaches to the premises, by the registration in the proper land registry office of a claim for lien on the title of the premises in accordance with this Part; and
(b) where the lien does not attach to the premises, by giving to the owner a copy of the claim for lien together with the affidavit of verification required by subsection (6). R.S.O. 1990, c. C.30, s. 34 (1).
Public highway
(2) Where a claim for lien is in respect of a public street or highway owned by a municipality, the copy of the claim for lien and affidavit shall be given to the clerk of the municipality. R.S.O. 1990, c. C.30, s. 34 (2).
Premises owned by Crown
(3) Where the owner of the premises is the Crown, the copy of the claim for lien and affidavit shall be given to the office prescribed by regulation, or, where no office has been prescribed, to the ministry or Crown agency for whom the improvement is made. R.S.O. 1990, c. C.30, s. 34 (3).
Railway right-of-way
(4) Where the premises is a railway right-of-way, the copy of the claim for lien and affidavit shall be given to the manager or any person apparently in charge of any office of the railway in Ontario. R.S.O. 1990, c. C.30, s. 34 (4).
Contents of claim for lien
(5) Every claim for lien shall set out,
(a) the name and address for service of the person claiming the lien and the name and address of the owner of the premises and of the person for whom the services or materials were supplied and the time within which those services or materials were supplied;
(b) a short description of the services or materials that were supplied;
(c) the contract price or subcontract price;
(d) the amount claimed in respect of services or materials that have been supplied; and
(e) a description of the premises,
(i) where the lien attaches to the premises, sufficient for registration under the Land Titles Act or the Registry Act, as the case may be, or
(ii) where the lien does not attach to the premises, being the address or other identification of the location of the premises. R.S.O. 1990, c. C.30, s. 34 (5).
Affidavit of verification
(6) A claim for lien shall be verified by an affidavit of the person claiming the lien, including a trustee of the workers’ trust fund where subsection 81 (2) applies, or of an agent or assignee of the claimant who is informed of the facts set out in the claim, and the affidavit of the agent or assignee shall state that the agent or assignee believes those facts to be true. R.S.O. 1990, c. C.30, s. 34 (6).
Preservation of general lien
(7) Subject to subsection 44 (4) (apportionment), a general lien shall be preserved against each of the premises that the person having the lien desires the lien to continue to apply against, and the claim against each premises may be for the price of the services or materials that have been supplied to all the premises. R.S.O. 1990, c. C.30, s. 34 (7).
Who may join in claim
(8) Any number of persons having liens upon the same premises may unite in a claim for lien, but where more than one lien is included in one claim, each person’s lien shall be verified by affidavit as required by subsection (6). R.S.O. 1990, c. C.30, s. 34 (8).
Liability for exaggerated claim, etc.
35. In addition to any other ground on which the person may be liable, any person who preserves a claim for lien or who gives written notice of a lien,
(a) for an amount which the person knows or ought to know is grossly in excess of the amount which the person is owed; or
(b) where the person knows or ought to know that the person does not have a lien,
is liable to any person who suffers damages as a result. R.S.O. 1990, c. C.30, s. 35.
What liens may be perfected
36. (1) A lien may not be perfected unless it is preserved. R.S.O. 1990, c. C.30, s. 36 (1).
Expiry of preserved lien
(2) A lien that has been preserved expires unless it is perfected prior to the end of the forty-five-day period next following the last day, under section 31, on which the lien could have been preserved. R.S.O. 1990, c. C.30, s. 36 (2).
How lien perfected
(3) A lien claimant perfects the lien claimant’s preserved lien,
(a) where the lien attaches to the premises, when the lien claimant commences an action to enforce the lien and, except where an order to vacate the registration of the lien is made, the lien claimant registers a certificate of action in the prescribed form on the title of the premises; or
(b) where the lien does not attach to the premises, when the lien claimant commences an action to enforce the lien. R.S.O. 1990, c. C.30, s. 36 (3).
Rules re sheltering
(4) A preserved lien becomes perfected by sheltering under a lien perfected by another lien claimant in respect of the same improvement in accordance with the following rules:
1. The preserved lien of a lien claimant is perfected by sheltering under the perfected lien of another lien claimant in respect of the same improvement where,
i. the lien of that other lien claimant was a subsisting perfected lien at the time when the lien of the lien claimant was preserved, or
ii. the lien of that other lien claimant is perfected in accordance with clause (3) (a) or (b) between the time when the lien of the lien claimant was preserved and the time that the lien of the lien claimant would have expired under subsection (2).
2. The validity of the perfection of a sheltered lien does not depend upon the validity, proper preservation or perfection of the lien under which it is sheltered.
3. A sheltered claim for lien is perfected only as to the defendants and the nature of the relief claimed in the statement of claim under which it is sheltered.
4. Upon notice given by a defendant named in a statement of claim, any lien claimant whose lien is sheltered under that statement of claim shall provide the defendant with further particulars of the claim for lien or of any fact alleged in the claim for lien. R.S.O. 1990, c. C.30, s. 36 (4).
General lien
(5) Subject to subsection 44 (4) (apportionment), a preserved general lien that attaches to the premises shall be perfected against each premises to which the person having the lien desires the lien to continue to apply. R.S.O. 1990, c. C.30, s. 36 (5).
Where period of credit extended
(6) A person who has preserved a lien, but who has extended a period of credit for the payment of the amount to which the lien relates, may commence an action for the purpose of perfecting the lien even though the period of credit has not at the time expired. R.S.O. 1990, c. C.30, s. 36 (6).
Expiry of perfected lien
37. (1) A perfected lien expires immediately after the second anniversary of the commencement of the action that perfected the lien, unless one of the following occurs on or before that anniversary:
1. An order is made for the trial of an action in which the lien may be enforced.
2. An action in which the lien may be enforced is set down for trial. 1994, c. 27, s. 42 (1).
Note: Subsection 37 (1), as re-enacted by the Statutes of Ontario, 1994, chapter 27, subsection 42 (1), does not affect any rights acquired by a person under a judgment or court order before December 9th, 1994. See: 1994, c. 27, s. 42 (3).
Motion under s. 46
(2) Where a lien has expired under subsection (1), a motion may be made under section 46. R.S.O. 1990, c. C.30, s. 37 (2).
Saving other rights
38. The expiration of a lien under this Act shall not affect any other legal or equitable right or remedy otherwise available to the person whose lien has expired. R.S.O. 1990, c. C.30, s. 38.
Right to information;
39. (1) Any person having a lien or who is the beneficiary of a trust under Part II or who is a mortgagee may, at any time, by written request, require information to be provided within a reasonable time, not to exceed twenty-one days, as follows:
from owner or contractor
1. By the owner or contractor, with,
i. the names of the parties to the contract,
ii. the contract price,
iii. the state of accounts between the owner and the contractor,
iv. a copy of any labour and material payment bond in respect of the contract posted by the contractor with the owner, and
v. a statement of whether the contract provides in writing that liens shall arise and expire on a lot-by-lot basis.
from contractor or subcontractor
2. By the contractor or a subcontractor, with,
i. the names of the parties to a subcontract,
ii. the state of accounts between the contractor and a subcontractor or between a subcontractor and another subcontractor,
iii. a statement of whether there is a provision in a subcontract providing for certification of the subcontract,
iv. a statement of whether a subcontract has been certified as complete, and
v. a copy of any labour and material payment bond posted by a subcontractor with the contractor or by a subcontractor with another subcontractor.
from owner
3. By an owner who is selling the owner’s interest in a premises that is a home, with,
i. the name and address of the purchaser, the sale price, the amount of the purchase price paid or to be paid prior to the conveyance, the scheduled date of the conveyance and the lot and plan number or other legal description of the premises as contained in the agreement of purchase and sale, and
ii. the date on which a permit authorizing occupancy or a certificate of completion and possession has been issued. R.S.O. 1990, c. C.30, s. 39 (1).
from mortgagee or unpaid vendor
(2) Any person having a lien or any beneficiary of a trust under Part II may, at any time, by written request, require a mortgagee or unpaid vendor to provide the person within a reasonable time, not to exceed twenty-one days, with,
(a) sufficient details concerning any mortgage on the premises to enable the person who requests the information to determine whether the mortgage was taken by the mortgagee for the purposes of financing the making of the improvement;
(b) a statement showing the amount advanced under the mortgage, the dates of those advances, and any arrears in payment including any arrears in the payment of interest; or
(c) a statement showing the amount secured under the agreement of purchase and sale and any arrears in payment including any arrears in the payment of interest. R.S.O. 1990, c. C.30, s. 39 (2).
by trustee or workers’ trust fund
(3) The trustee of a workers’ trust fund may at any time by written request require any contractor or subcontractor to permit the trustee, within a reasonable time after making the request, not to exceed twenty-one days, to inspect the payroll records of all workers who are beneficiaries of the fund, and who have supplied labour to the making of the improvement, and who are employed by the contractor or the subcontractor. R.S.O. 1990, c. C.30, s. 39 (3).
respecting publication of certificate of substantial performance
(4) A contractor shall, upon written request whenever made to the contractor by any person, within a reasonable time furnish in writing to the person the date of publication and the name of the construction trade newspaper in which a copy of a certificate of substantial performance has been published under subsection 32 (1). R.S.O. 1990, c. C.30, s. 39 (4).
Liability for failure to provide information
(5) Where a person, who is required under subsection (1), (2), (3) or (4) to provide information or access to information, does not provide the information or access to information as required or knowingly or negligently mis-states that information, the person is liable to the person who made the request for any damages sustained by reason thereof. R.S.O. 1990, c. C.30, s. 39 (5).
Order by court to comply with request
(6) Upon motion, the court may at any time, whether or not an action has been commenced, order a person to comply with a request that has been made to the person under this section and, when making the order, the court may make any order as to costs as it considers appropriate in the circumstances, including an order for the payment of costs on a substantial indemnity basis. R.S.O. 1990, c. C.30, s. 39 (6); 2006, c. 21, Sched. C, s. 102 (1).
Cross-examination on claim for lien
40. (1) Any person who has verified a claim for lien that has been preserved is liable to be cross-examined without an order on the claim for lien at any time, irrespective of whether an action has been commenced. R.S.O. 1990, c. C.30, s. 40 (1).
Who may participate
(2) There shall be only one examination under subsection (1), but the contractor, the payer of the lien claimant, and every person named in the claim for lien who has an interest in the premises are entitled to participate therein. R.S.O. 1990, c. C.30, s. 40 (2).
Notice
(3) Any person intending to examine a person under subsection (1) shall give at least seven days notice of the examination specifying the time and place for the examination to,
(a) the person to be examined or the person’s solicitor;
(b) every other person named in the claim for lien as having an interest in the premises;
(c) the contractor; and
(d) the payer of the lien claimant. R.S.O. 1990, c. C.30, s. 40 (3).
Application of rules of court
(4) The rules of court pertaining to examinations apply, with necessary modifications, to cross-examinations under this section. R.S.O. 1990, c. C.30, s. 40 (4).
PART VII
DISCHARGE OF PRESERVED OR PERFECTED LIENS
Discharge of lien and withdrawal of written notice of lien
Discharge of lien claim by release
41. (1) A preserved or perfected lien may be discharged,
(a) where the lien attaches to the premises, by the registration of a release in the prescribed form on the title to the premises and the release shall, except where the lien claimant is a corporation, be supported by an affidavit of execution; or
(b) where the lien does not attach to the premises, by giving a release in the prescribed form to the owner, in the manner set out in section 34 for the giving of copies of the claim for lien. R.S.O. 1990, c. C.30, s. 41 (1).
Withdrawal of written notice of lien
(2) A written notice of a lien may be withdrawn by giving a withdrawal in writing to the person to whom the written notice of a lien was given, and a payer given the withdrawal shall, in respect of the operation of subsection 24 (2), be in the same position as if the written notice of a lien had never been given. R.S.O. 1990, c. C.30, s. 41 (2).
Discharge of general lien
42. A preserved or perfected general lien may be discharged against any one or more of the premises that are subject to it, without affecting its application to any other premises to which it applies, by the registration of a release in the prescribed form on the title to the premises released. R.S.O. 1990, c. C.30, s. 42.
Postponement of lien claim
43. A preserved or perfected lien may be postponed in favour of the interest of another person in the premises by the registration on the title to t